time and work using LCM, no fractions

Asked by Irfan Qureshi 1 month ago 2 answers 9 votes

A does a job in 12 days, B in 18.

total work = LCM(12,18) = 36 units
A = 3 units/day, B = 2 units/day
together 5/day -> 36/5 = 7.2 days

works for pipes and cisterns too, leak is just negative units

2 answers

Swati Mishra1 month agoMost voted3

this is how my coaching sir taught it. never going back to fractions

Priya Sharma1 month ago2

also easy for "A leaves after 4 days" type questions, just subtract A's units